Reconstruction Day 10

Today the electrician for the project began the wiring.  He will be coming back hopefully to complete it tomorrow.  Once the electrical wiring is done MCC can finish the roofing.  In the mean time, the MCC crew is installing windows.  They have put in several of the windows already and will continue working on them tomorrow.

The completed shell with some of the windows installed

The interior of the garage

Looking through where the front door will soon be

Installing some of the windows

One window installed, one awaiting installation

The beginning of the wiring installed by the electrician today