Sunday, September 23, 2012

Reconstruction Day 9

On Friday MCC installed the wood blocking and sleepers for the garage roof.  They also finished the roof sheathing and covered it with a protective tarp for the the weekend.  the next step is installing the inner-wall wiring, which will be followed by roof insulation, fascia panels and roofing.

Installing the garage roof wood blocking and sleepers

Garage roof sheathing finished

Tarps covering the unfinished roof awaiting wiring, insulation, and roofing material